Ridgeline
SM

Dennis Kowalski - Production

8801 N Oak Trafficway · $38,600 contract · squares · Lifetime Architectural

Not ReadyPre-Production

Production readiness

6 OF 11 COMPLETE

5 items are blocking install.

GAF Timberline HDZ

Lifetime Architectural

GAF System Plus - 50 year limited

Selected color

Not selected

Options not sent

Next action

Resolve shingle color confirmed

Owner Tony Alvarez · sold by Sarah Mitchell

Production summary

Stage
Pre-Production
Install date
Pending
Crew
Unassigned
Materials
Not Ordered
Permit
Pending
Color
Not selected
Production manager
Tony Alvarez
Photos
14

Production timeline

Production activity appears here.